Service Interruption: April 7-10, 2026
- Mar 31
- 3 min read
Updated: Apr 10
April 7, 2026 (Tuesday)
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Lahug by facilitating installation of distribution transformer. |
Areas Affected: | Portion of Lahug, Cebu City, along La Guardia St., St. Anthony St., and St. Lawrence St. |
Map: | ![]() |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Polog by facilitating installation of primary pole. |
Areas Affected: | Portion of Polog, Consolacion, along portion of Danglag-Polog Road |
Map: | ![]() |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Bulacao by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of Bulacao, Talisay City, along portions of Ottawa St. |
Map: | ![]() |
Time: | 9:00 AM to 1:00 PM (4hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Banilad by facilitating installation of guy wire and removal of secondary pole and rerouting of primary lines. |
Areas Affected: | Portion of Banilad, Cebu City, along Cebu Country Club. |
Map: | ![]() |
April 7-8, 2026 (Tuesday - Wednesday)
Time: | 10:00 PM of April 7 to 6:00 AM of April 8 (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Mambaling & San Roque by facilitating installation of distribution transformer. |
Areas Affected: | Portion of Mambaling & San Roque, Cebu City, along portions of F. Vistel Street, L. Gabuya Street, & Srp Back Road. |
Map: | ![]() |
April 8, 2026 (Wednesday)
Time: | 9:00 AM to 5:00 PM (8hrs) 𝐂𝐀𝐍𝐂𝐄𝐋𝐋𝐄𝐃 |
Purpose: | To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Calero by facilitating relocation of primary pole as per customer request. |
Areas Affected: | Portion of Calero, Liloan, along Pagutlan Road. |
Map: | ![]() |
April 9, 2026 (Thursday)
Time: | 8:00 AM to 4:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tubod by facilitating primary line maintenance. |
Areas Affected: | Portion of Tubod, Minglanilla |
Map: | ![]() |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Apas by facilitating installation of primary pole. |
Areas Affected: | Portion of Apas, Cebu City, along portion of Wilson St. |
Map: | ![]() |
April 10, 2026 (Friday)
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Apas , Busay & Lahug by facilitating extension of primary lines (line stringing). |
Areas Affected: | Portion of Apas, Busay & Lahug, Cebu City, along portion of Cebu Transcentral Highway. |
Map: | ![]() |
Time: | 9:00 AM to 12:00 PM (3hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Tapul by facilitating installation of distribution transformer. |
Areas Affected: | Portion of Tapul, Talisay City. |
Map: | ![]() |
Time: | 9:00 AM to 5:00 PM (8hrs) 𝐂𝐀𝐍𝐂𝐄𝐋𝐋𝐄𝐃 |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tisa by facilitating replacement of rotten pole. |
Areas Affected: | Portion of Tisa, Cebu City, along portion of Mohon. |
Map: | ![]() |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Cabancalan by facilitating replacement of distribution transformer. |
Areas Affected: | Portion of Cabancalan, Mandaue City, along portion of P. Remedio St. |
Map: | ![]() |
Time: | 8:00 AM to 10:00 AM (2hrs) |
Purpose: | To facilitate cutting of loops for isolation of working area |
Areas Affected: | Portion of Tayud & Calero, Consolacion & Liloan, along portions of along portions of Bayview Road, Cebu North Coastal Road, E. Binabag Road, & Pondol Street. |
Map: | ![]() |
Time: | 5:00 PM to 6:00 PM (1hr) |
Purpose: | To facilitate installation of loops for energization of working area |
Areas Affected: | Portion of Tayud & Calero, Consolacion & Liloan, along portions of Bayview Road, Cebu North Coastal Road, E. Binabag Road, & Pondol Street. |
Map: | ![]() |
Time: | 8:00 AM to 6:00 PM (10hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Tayud & Calero by facilitating extension of primary lines (line stringing) |
Areas Affected: | Portion of Tayud & Calero, Consolacion & Liloan, along portions of Cebu North Coastal Road, Consolacion-Tayud-Liloan Roa & Pagutlan Road. |
Map: | ![]() |
Time: | 9:00 AM to 5:00 PM (8hrs) 𝐂𝐀𝐍𝐂𝐄𝐋𝐋𝐄𝐃 |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tangke by facilitating removal of distribution transformer |
Areas Affected: | Portion of Tangke, Talisay City, specifically Cebu South Harbor & Container Terminal Corporation. |
Map: | ![]() |