December 7, 2025 (Sunday)

Time:

8:00 AM to 10:00 AM (2hrs)

Purpose:

To facilitate cutting of loops for isolation of working area.


Areas Affected:

Portion of Calamba, Duljo Fatima, Pahina Central, San Nicolas Proper & Sawang Calero, Cebu City, along portions of Lakandula Street, Natalio Bacalso Avenue, P. Sanchez Street, B. Aranas Street, Panganiban Street, & Sanciangco Street.


Time:

 5:00 PM to 6:00 PM (1hr)

Purpose:

To facilitate installation of loops for energization of working area.


Areas Affected:

Portion of Calamba, Duljo Fatima, Pahina Central, San Nicolas Proper & Sawang Calero, Cebu City, along portions of Lakandula Street, Natalio Bacalso Avenue, P. Sanchez Street, B. Aranas Street, Panganiban Street, & Sanciangco Street.


Time:

8:00 AM to 6:00 PM (10hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Calamba, Duljo Fatima, Pahina Central, San Nicolas Proper & Sawang Calero by facilitating rerouting of primary lines.


Areas Affected:

Portion of Calamba, Duljo Fatima, Pahina Central, San Nicolas Proper & Sawang Calero, Cebu City, along portions of Lakandula Street, Natalio Bacalso Avenue, P. Sanchez Street, B. Aranas Street, Panganiban Street, & Sanciangco Street.


Time:

8:00 AM to 5:00 PM (9hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. San Nicolas Proper by facilitating rerouting of primary lines.


Areas Affected:

Portion of San Nicolas Proper, Cebu City, including portions along Lakandula St. & Candido Padilla St.

Time:

8:00 AM to 10:00 AM (2hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Basak, Canduman, Casili, Cubacub, & Pagsabungan by facilitating replacement of line device’s control box

Areas Affected:

Portions of Basak, Canduman, Cubacub, & Pagsabungan, Mandaue City, and Cubacub & Casili, Consolacion along portions of Bombil Street, Cubacub Street, D.L. Bihag Street, H. Abellana Street, & P.I. Ouano Street

December 8, 2025 (Monday)

Time:

8:00 AM to 5:00 PM (9hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Cambinocot & Lusaran by facilitating primary line upgrading.

Areas Affected:

Portion of Cambinocot & Lusaran, Cebu City, including portion along Lusaran-Cambinocot Road.

Time:

 8:00 AM to 5:00 PM (9hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Lusaran by facilitating primary line upgrading.

Areas Affected:

Portion of Cebu City (Lusaran) including portion along Lusaran-Cambinocot Road.

December 9, 2025 (Tuesday)

Time:

 9:00 AM to 5:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Tolotolo by facilitating relocation of primary pole as per customer request.


Areas Affected:

Portion of Tolotolo, Consolacion, along Tolotolo Rd., Kamatisan Rd.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Cuanos by facilitating installation of distribution transformer.

Areas Affected:

Portion of Cuanos,Minglanilla, along Brgy. Camp 8 Rd.

Time:

 9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving North Reclamation Area by facilitating installation of primary pole.

Areas Affected:

Portion of North Reclamation Area, Cebu City, including portions along Juan Luna Ave. Extn. & N 7th Road.

Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Bacayan, San Jose, Talamban & Tawason by facilitating relocation of primary pole as per customer request.

Areas Affected:

Portion of Bacayan, San Jose, Talamban, Cebu City & Tawason, Mandaue City, including portions along Talamban Road, Kauswagan Road, San Jose Road & A. Minoza Road including Mary Ville Talamban.

Time:

9:00 AM to 2:00 PM (5hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Mabolo by facilitating tapping of service entrance wire

Areas Affected:

Portion of Mabolo, Cebu City, including portion along H. Joaquino Street.

Time:

9:00 AM to 12:00 PM (3hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Pooc by facilitating primary line maintenance.

Areas Affected:

Portion of Pooc, Talisay City, including portion along Congressman Bacaltos Road.

December 10, 2025 (Wednesday)

Time:

 9:00 AM to 3:00 PM (6hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Cambinocot & Mabini by facilitating reconstruction of primary lines.

Areas Affected:

Portion of Cambinocot & Mabini, Cebu City, including portion along Going to Ga-ang Paril Chapel Road.

Time:

 9:00 AM to 4:00 PM (7hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Pulangbato by facilitating upgrading of distribution transformer.

Areas Affected:

Portion of Pulangbato, Cebu City along portions of Kahayahay Village.


Time:

 9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Pulangbato by facilitating upgrading of distribution transformer.

Areas Affected:

Portion of Subangdaku, Mandaue City along portions of M. Logarta Avenue.

Time:

8:00 AM to 3:00 PM (7hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Manduang & Tubod by facilitating primary line maintenance

Areas Affected:

Portion of Manduang & Tubod, Minglanilla including portions along Brgy. Manduang Road.


December 11, 2025 (Thursday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Casili by facilitating reconstruction of primary lines.

Areas Affected:

Portion of Casili, Consolacion,  including portion of Blossom Ville Subdivision.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Bulacao & Cadulawan by facilitating upgrading of distribution transformer.

Areas Affected:

Portion of Casili, Consolacion,  including portion of Blossom Ville Subdivision.

December 11-12, 2025 (Thursday-Friday)

Time:

10:00 PM of December 11 to 6:00 AM of December 12 (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Mabolo by facilitating primary line maintenance.

Areas Affected:

Portion of Mabolo, Cebu City, along portions of M. Logarta Avenue.

December 12, 2025 (Friday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Casili by facilitating reconstruction of primary lines.

Areas Affected:

Portion of Casili, Mandaue City, along portions of Cubacub St.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Subangdaku by facilitating installation of distribution transformer and reconstruction of primary pole.

Areas Affected:

Portion of Subangdaku, Mandaue City along portions of Lopez Jaena St.

December 13, 2025 (Saturday)

Time:

8:00 AM to 5:00 PM (9hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Labangon by facilitating reconstruction of primary lines.


Areas Affected:

Portion of Labangon, Cebu City, along portions of N. Bacalso Avenue near Cebu Institute of Technology - University.

Time:

 8:00 AM to 6:00 PM (10hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Talamban by facilitating extension of primary lines (line stringing).


Areas Affected:

Portion of Talamban, Cebu City including portions of Sunny Hills Subdivision along Sunrise Dr.