Start Your New Connection

Get Connected — Follow the Steps to Apply

Step 1
Step 2

Secure an Electrical Permit

Get an Electrical Permit from the Office of the Building Official (OBO.)

Hire an accredited electrician or electrical practitioner for metering setup.

Hire an Electrical Practitioner

​Submit the Documents

Application Endorsement

Settle Required Payments

Sign the Service Agreement

Installation & Energization

Step 3
Step 4
Step 5
Step 6
Step 7

Electrician or electrical practitioner endorses your application.

Pay your bill deposit and a special deposit if required based on the inspection load listing, at any of our authorized payment centers.

Sign the Electric Service Agreement to finalize your application.

Meter installation and energization is within 2–3 working days after payment and contract signing.

Screenshot 2025-10-28 114813.png
Screenshot 2025-10-28 114821.png
Screenshot 2025-10-28 115649.png
Screenshot 2025-10-28 115704.png
Screenshot 2025-10-28 132431.png
Screenshot 2025-10-28 132441.png
Screenshot 2025-10-28 132457.png
bottom of page