Service Interruption: January 25-31, 2025

January 25, 2025 ( Saturday)

Time:

4:00 PM to 5:00 PM (1hr)

Purpose:

To facilitate installation of loops for energization of working area.

Areas Affected:

Portion of Cebu City (Babag & Bonbon) along Bonbon-Sudlon 2 Brgy Road including portions of Sitio Maowan and Sitio Hamtik.

Time:

8:00 AM to 9:00 AM (1hr)

Purpose:

To facilitate cutting of loops for isolation of working area.

Areas Affected:

Portion of Cebu City (Babag & Bonbon) along Bonbon-Sudlon 2 Brgy Road including portions of Sitio Maowan and Sitio Hamtik.

Time:

8:00 AM to 5:00 PM (9hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Bonbon by facilitating primary line upgrading.

Areas Affected:

Portion of Cebu City (Bonbon) along Bonbon-Sudlon 2 Brgy Road including portions of Sitio Camarin, as well as Golden Cowrie Franchising.

Time:

2:00 PM to 5:00 PM (3hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Buhisan , Labangon & Tisa by facilitating removal of line device hardware (DS/FCO/Insulator/LBS).

Areas Affected:

Portion of Cebu City (Buhisan , Labangon & Tisa) along portions of Cebu Hills South Road , Katipunan Road, & Mutra Road, including portions of Sitios Banika , Caimbol , Calma , Calomboyan , Dosdos , Fatima , Filtro , Hidden Valley , Jerusalim , Magtinabangay , Mangga , Mohon , Morehai , Motra , Pilipog , Sinai , Sineguilas , Sunflower Hoa , Tabay Lawom , Tahna, & Upmora, and Dosdos Village , Hills View Village , Odevillas Subdivision , Sinai Homes , South Hills, & Villa Ollina Home Owners Association Inc.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Kasambagan by facilitating reconstruction of primary lines.

Areas Affected:

Portion of Cebu City (Kasambagan) along portion of Paradise Village.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Cotcot by facilitating replacement of rotten pole.

Areas Affected:

Portion of Liloan (Cotcot) along portions of Purok Mangga Uno.

January 26, 2025 (Sunday)

Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Tayud by facilitating tapping of primary lines.

Areas Affected:

Portion of Liloan (Tayud) including portion of Sitio Simborio.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Sto. Niño by facilitating extension of primary lines (line stringing).

Areas Affected:

Portion of Cebu City (Sto. Niño) including portion along D. Jakosalem Street, Bayanihan Multi-Purpose Coop., Cebu City Government, and Cebu Integrated Arrastre Inc.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. San Roque & Sto. Niño by facilitating installation of primary pole and installation of distribution transformer.

Areas Affected:

Portion of Cebu City (San Roque & Sto. Niño) along P. Burgos St., Legaspi St. including Cebu Landmasters Inc., Globe Telecom Inc., Che Yong Investment, Brgy Snr Sto Nino-Brgy Hall Tm, Confrat of our Lady, Catholic Women League, Lianting Dev Corp.

Time:

8:00 AM to 4:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Lawaan II & San Isidro by facilitating 69kV Lines Stringing.

Areas Affected:

Portion of Talisay City (Lawaan II & San Isidro) along Cebu South Coastal Road including portions of Sitio Oregano and Zone 4 Isla Verde as well as Gawad Kalinga Village and Corazon Village.

Time:

3:00 PM to 4:00 PM (1hr)- CANCELLED

Purpose:

To facilitate installation of loops for energization of working area.

Areas Affected:

Portion of Talisay City (San Isidro & Tabunok) along portion of San Isidro Road, including portions of Sitios Cabugnaan , Mahayag , Mahayahay , Matibanganon , Neighborhood , Panaghiusa , Pangpang, & Tiago, and Canton Village , Greenville Subdivision , Largo Compound , Ruiz Compound , Sabido Compound , San Isidro Village , South Glendale Subdivision , Sta. Theresa Village 2 , Sto. Nino Village , Vergara Village , Victoria Village, & Villa Sta Cruz.

Time:

8:00 AM to 9:00 AM (1hr)- CANCELLED

Purpose:

To facilitate cutting of loops for isolation of working area.

Areas Affected:

Portion of Talisay City (San Isidro & Tabunok) along portion of San Isidro Road, including portions of Sitios Cabugnaan , Mahayag , Mahayahay , Matibanganon , Neighborhood , Panaghiusa , Pangpang, & Tiago, and Canton Village , Greenville Subdivision , Largo Compound , Ruiz Compound , Sabido Compound , San Isidro Village , South Glendale Subdivision , Sta. Theresa Village 2 , Sto. Nino Village , Vergara Village , Victoria Village, & Villa Sta Cruz.

Time:

8:00 AM to 4:00 PM (8hrs)-CANCELLED

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Tabunok by facilitating relocation of primary pole as per customer request.

Areas Affected:

Portion of Talisay City (Tabunok) along San Isidro Road and Palmview Street.

January 27, 2025 (Monday)

Time:

9:00 AM to 11:00 AM (2hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Apas , Lahug & San Antonio by facilitating removal of primary pole.

Areas Affected:

Portion of Cebu City (Apas , Lahug & San Antonio) including portions of Sitios Fatima , Mahayahay , Panabang , Plaza , Sto. Nino, & Tangke, and Nivel Hills & San Antonio Village.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Guadalupe by facilitating relocation of primary pole for upcoming projects.

Areas Affected:

Portion of Cebu City (Guadalupe) along J. Fortich St, Horseshoe Drive and I. Limkakeng Street.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Calamba by facilitating relocation of primary pole as per customer request.

Areas Affected:

Portion of Cebu City (Calamba) along V. Rama Ave, A. Lopez St., Lucio Lopez Drive.

January 28, 2025 (Tuesday)

Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Sacsac by facilitating reconstruction of primary lines.

Areas Affected:

Portion of Consolacion (Sacsac) along Sacsac Rd. including portions of Villarita.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Malubog by facilitating extension of primary lines (line stringing).

Areas Affected:

Portion of Cebu City (Malubog) including portions along Sitio Lower Malubog.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Malubog by facilitating extension of primary lines (line stringing).

Areas Affected:

Portion of Cebu City (Malubog) along Sitio Lower Malubog.

January 29-30, 2025 (Wednesday-Thursday)

Time:

10:00 PM of January 29 to 6:00 AM of January 30 (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Casuntingan by facilitating 69kV pole installation and dressing.

Areas Affected:

Portion of Mandaue City (Casuntingan) along M.L Quezon Avenue and P. Ceniza St. including portions of F.B Seno Cmpd.

January 30, 2025 (Thursday)

Time:

9:00 AM to 1:00 PM (4hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Zapatera by facilitating primary line maintenance.

Areas Affected:

Portion of Cebu City (Zapatera) along Sikatuna St.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Alpaco by facilitating relocation of primary pole as per customer request.

Areas Affected:

Portion of City of Naga (Alpaco) along Mayana Rd. including portions of Purok Seabod.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Quiot by facilitating upgrading of distribution transformer.

Areas Affected:

Portion of Cebu City (Quiot) along Antuwaga Rd. including portions of San Carlos Heights.

January 31, 2025 (Friday)

Time:

8:00 AM to 4:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. San Vicente by facilitating relocation of primary pole as per customer request.

Areas Affected:

Portion of Liloan (San Vicente) including portions of Sitio Bugwak, Sitio Curva & Sitio Limogmog, Villa Amalia Subdivision, San Miguel Settlers Subdivision, and Villa Ayuda Subdivision.


bottom of page