July 5, 2026 (Sunday)
Time: | 6:00 AM to 2:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Cansaga & Poblacion Occidental by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of Cansaga & Poblacion Occidental, Consolacion, along Cebu North Road, M. Pepito Rd., going to Cansaga Brgy Hall. |
Map: | ![]() |
Time: | 6:00 AM to 7:30 AM (1.5hrs) |
Purpose: | To ensure the safety of personnel working on the line. |
Areas Affected: | Portion of Balud, Lantawan, Panadtaran, Poblacion South, Sangat & Tonggo, San Fernando, along Cebu South Road. |
Map: | ![]() |
Time: | 3:30 PM to 5:00 PM (1.5hrs) |
Purpose: | To ensure the safety of personnel working on the line. |
Areas Affected: | Portion of Balud, Lantawan, Panadtaran, Poblacion South, Sangat & Tonggo, San Fernando, along portions of Cebu South Road. |
Map: | ![]() |
Time: | 7:30 AM to 3:30 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Balud, Greenhills, Lantawan, Panadtaran, Poblacion South, Sangat & Tonggo by facilitating 69kV Lines Stringing. |
Areas Affected: | Portion of Balud, Greenhills, Lantawan, Panadtaran, Poblacion South, Sangat & Tonggo, San Fernando, along Cebu South Road. |
Map: | ![]() |
Time: | 8:00 AM to 4:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. San Vicente by facilitating extension of primary lines (line stringing). |
Areas Affected: | Portion of San Vicente, Liloan, along portions of Bajac Road and Danarra North. |
Map: | ![]() |
Time: | 8:00 AM to 4:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tipolo by facilitating installation of primary pole and reconstruction of primary lines and installation of distribution transformer. |
Areas Affected: | Portion of Tipolo, Mandaue City, including portions of Singson Village. |
Map: | ![]() |
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To increase the capacity of the distribution system serving North Reclamation Area by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of North Reclamation Area, Cebu City, along J. de Veyra St. |
Map: | ![]() |
July 7, 2026 (Tuesday)
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Tipolo by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of Tipolo, Mandaue City, along Lopez Jaena St. |
Map: | ![]() |
Time: | 9:00 AM to 1:00 PM (4hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Guadalupe by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of Guadalupe, Cebu City, along Lomboy St., Manga St., Chico St. |
Map: | ![]() |
Time: | 9:00 AM to 3:00 PM (6hrs) 𝐂𝐀𝐍𝐂𝐄𝐋𝐋𝐄𝐃 |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tisa by facilitating isolation of equipment due to safety concern. |
Areas Affected: | Portion of Tisa, Cebu City, along F. Pacana St. |
Map: | ![]() |
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Bairan, Bugho, Cabungahan, Inoburan, Jaguimit, Langtad, Lutac, Mainit & Patag by facilitating reconstruction of primary lines. |
Areas Affected: | Portion of San Fernando & City of Naga (Bairan, Bugho, Cabungahan, Inoburan, Jaguimit, Langtad, Lutac, Mainit & Patag) including portions of Sitios Atbang, Atis, Babao, Badyang, Bungtod, Busay, Cansimundong, Dita, Guindolman, Ka Ectay, Kabilyok, Katuling, Lalid, Lomboy, Ludo, Mohon Lagtang, Orchids, Regla, Sambag, Tal-Ot, Tambis, & Tuburan. |
Map: | ![]() |
Time: | 9:00 AM to 12:00 PM (3hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Sta. Cruz by facilitating shutdown request from a customer. |
Areas Affected: | Portion of Sta. Cruz, Liloan, along St. Cruz Rd. including portions of Purok Lutheran. |
Map: | ![]() |
July 7 - July 8, 2026 (Tuesday- Wednesday)
Time: | 10:00 PM of July 7 to 6:00 AM of July 8 (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tulay & Tungkop by facilitating 69kV pole installation and dressing. |
Areas Affected: | Portion of Tulay & Tungkop, Minglanilla, along portions of Tungkop Rd. and A. Apostol St. |
Map: | ![]() |
July 8, 2026 (Wednesday)
Time: | 9:00 AM to 12:00 PM (3hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tilhaong by facilitating reconstruction of primary lines. |
Areas Affected: | Portion of Tilhaong, Consolacion, along Diversion Rd. including Apao Ville Subd. |
Map: | ![]() |
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Bacayan by facilitating shutdown request from a customer. |
Areas Affected: | Portion of Bacayan, Cebu City, along A. Minoza St., Huyong-huyong Rd., G. Seno Ext. |
Map: | ![]() |
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Yati by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of Yati, Liloan, along portion of Cebu North Road. |
Map: | ![]() |
July 8- July 9 , 2026 (Wednesday- Thursday)
Time: | 10:00 PM of July 8 to 6:00 AM of July 9 (8hrs) 𝐂𝐀𝐍𝐂𝐄𝐋𝐋𝐄𝐃 |
Purpose: | To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Kalubihan & Pahina Central by facilitating relocation of primary pole as per customer request. |
Areas Affected: | Portion of Kalubihan & Pahina Central, Cebu City, along portions of A. Borromeo Street, Climaco, Colon Street, Leon Kilat, & P. Lopez Street. |
Map: | ![]() |
July 9, 2026 (Thursday)
Time: | 9:00 AM to 2:00 PM (5hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Cotcot by facilitating isolation of equipment due to safety concern. |
Areas Affected: | Portion of Cotcot, Liloan, along Fatima Rd., going to Tiltilon Elementary School. |
Map: | ![]() |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Poblacion Pardo by facilitating tapping of service entrance wire. |
Areas Affected: | Portion of Poblacion Pardo, Cebu City, along A. Gabuya St. |
Map: | ![]() |
Time: | 8:00 AM to 2:00 PM (6hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Babag, Busay & Malubog by facilitating repair or replacement of damaged line hardware and line equipment. |
Areas Affected: | Portion of Babag, Busay & Malubog, Cebu City, along portions of Cebu Transcentral Highway, Roosevelt Drive and Cebu Tops Rd. |
Map: | ![]() |
July 10, 2026 (Friday)
Time: | 9:00 AM to 2:00 PM (5hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Jubay by facilitating tapping of service entrance wire. |
Areas Affected: | Portion of Jubay, Liloan, along Cabancalan Jubay Rd. |
Map: | ![]() |
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Guadalupe by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of Guadalupe, Cebu City, along portions of M. Veloso Street. |
Map: | ![]() |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tayud by facilitating installation of distribution transformer and installation of primary pole. |
Areas Affected: | Portion of Tayud, Consolacion, along portions of Cebu-North Coastal Road and roads leading to Lim Seng Hua Food Products Corporation. |
Map: | ![]() |
July 10, 2026 (Friday) - July 11, 2026 (Saturday)
Time: | 10:00 PM of July 10 to 6:00 AM of July 11 (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tulay by facilitating installation of line device hardware (DS/FCO/LBS) and installation of primary pole and reconstruction of primary lines. |
Areas Affected: | Portion of Tulay, Minglanilla, along 18 de Julio St., A. Apostol St. |
Map: | ![]() |
July 11, 2026 (Saturday)
Time: | 7:00 AM to 5:00 PM (10hrs) |
Purpose: | To improve the reliability of the distribution system serving Cebu I.T. Park by facilitating switchgear PMS. |
Areas Affected: | Portion of Cebu I.T. Park, Cebu City, along portions of Geonzon St. & Salinas Drive. |
Map: | ![]() |
Time: | 8:00 AM to 4:00 PM (8hrs) |
Purpose: | To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Cogon Pardo & Poblacion Pardo by facilitating relocation of primary pole as per customer request. |
Areas Affected: | Portion of Cogon Pardo & Poblacion Pardo, Cebu City, along L. Gabuya St., A. Gabuya St., Gabuya St., F.Jaca St., & J. Tabura St. |
Map: | ![]() |
July 11, 2026 (Saturday) - July 12, 2026 (Sunday)
Time: | 10:00 PM of July 11 to 5:00 AM of July 12 (7hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Basak , Casili , Jagobiao , Poblacion Orriental by facilitating primary line maintenance. |
Areas Affected: | Portion of Mandaue City & Consolacion, Basak , Casili , Jagobiao , Poblacion Orriental, along portions of Cattleya St. , C.Congson Road , Cebu North Road, & Tomas P. Go Rd. |
Map: | ![]() |
Time: | 10:00 PM of July 11 to 6:00 AM of July 12 (8hrs) - 𝐂𝐀𝐍𝐂𝐄𝐋𝐋𝐄𝐃 |
Purpose: | To improve the reliability of the distribution system serving Brgy. Jubay & Poblacion by facilitating reconstruction of primary lines |
Areas Affected: | Portion of Liloan, Jubay & Poblacion, along portions of Central National Hwy. |
Map: | ![]() |