March 22, 2026 (Sunday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Guadalupe by facilitating replacement of primary pole.

Areas Affected:

Portion of Guadalupe, Cebu City, along GoldenVille Banawa, Guadalupe Cebu City.

Map:

Time:

8:00 AM to 4:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Mambaling by facilitating installation of automatic reclosing device (recloser).

Areas Affected:

Portion of Mambaling, Cebu City, Road going to SRP Welcome Hill Tower including South Coast City, District Square, SM Arena Seaside City.

Map:

Time:

9:00 AM to 12:00 PM (3hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Banilad by facilitating tapping of service entrance wire.

Areas Affected:

Portion of Banilad, Cebu City, along portions of Doña Rita Village.

Map:


Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Tungkil & Pakigne by facilitating relocation of primary pole that is affected by road widening project.

Areas Affected:

Portion of Tungkil & Pakigne, Minglanilla, along portions of Countryside Village, including portions of Sitios Dapdap, Noah, San Roque, & Sto. Nino, and Agustina Village, Deca Homes Subdivision, Minglanilla Homes, Tenese Feedmill Compd, Villa Celina Subdivision, & Villa Feliza Subdivision.

Map:

Time:

7:00 AM to 3:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Lahug by facilitating tapping of service entrance wire.

Areas Affected:

Portion of Lahug, Cebu City, along Sanson Rd.

Map:

Time:

8:00 AM to 2:00 PM (6hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Basak San Nicolas, Calamba, Mambaling & Punta Princesa by facilitating installation of automatic reclosing device (recloser).

Areas Affected:

Portion of Basak San Nicolas, Calamba, Mambaling & Punta Princesa, Cebu City, along portions of Natalio B. Bacalso Avenue  & Tres De Abril.

Map:

March 23, 2026 (Monday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Guadalupe by facilitating replacement of primary pole.

Areas Affected:

Portion of Guadalupe, Cebu City, along Cleveland St.

Map:

March 24, 2026 (Tuesday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Bulacao by facilitating installation of primary pole.

Areas Affected:

Portion of Bulacao, Cebu City, along Urban Cabancalan 1 Rd.

Map:

Time:

 9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Tingub by facilitating installation of distribution transformer.

Areas Affected:

Portion of Tingub, Mandaue City, along portions of P. Sanchez / Pagsabungan Road.

Map:

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Pit-os by facilitating relocation of primary pole as per customer request.

Areas Affected:

Portion of Pit-os, Cebu City, along portions of Upper Sacsac Road as well as  Deo Residences (Deo Homes).

Map:

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Tayud by facilitating upgrading of distribution transformer.

Areas Affected:

Portion of Tayud, Consolacion, along portions of Cebu-North Road as well as near Barangay Tayud Gymnasium.

Map:

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Guadalupe by facilitating upgrading of distribution transformer.

Areas Affected:

Portion of Guadalupe, Cebu City, along A. Abellana St.

Map:

Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To improve the reliability of the distribution system serving South Reclamation Area by facilitating tapping of service entrance wire.

Areas Affected:

Portion of South Reclamation Area, Cebu City, along El Pardo Rd.

Map:

March 25, 2026 (Wednesday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. East Poblacion & North Poblacion by facilitating reconstruction of primary lines.

Areas Affected:

Portion of City of East Poblacion & North Poblacion, Naga, along Cebu South Rd., Bonifacio St.,  & G. Mendoza.

Map:

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. East Poblacion by facilitating primary line upgrading.

Areas Affected:

Portion of East Poblacion, City of Naga, along Cebu South Road.

Map:

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Busay & Lahug by facilitating reconstruction of primary lines.

Areas Affected:

Portion of Busay & Lahug, Cebu City, along Faith St., Justice St., Temperance St., Prudence St., Hope St., Charity St., & Salinas Ext.

Map:

Time:

5:00 AM to 6:00 AM (1hr)

Purpose:

To facilitate cutting of loops for isolation of working area.

Areas Affected:

Portion of Mandaue City & Consolacion (Basak, Cansaga, Casili, Jagobiao, Jugan, Lamac, Pitogo, Poblacion Occidental, Poblacion Oriental) along portions of Cebu National Road, Central Nautical Highway, Laray Road, M. Pepito Street, Maglasang Road, Semblante Street, & Tomas P. Go Road.

Map:

March 25, 2026 (Wednesday) - March 26, 2026 (Thursday)

Time:

10:00 PM of March 25 to 6:00 AM of March 26 (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Poblacion Occidental & Poblacion Orriental by facilitating primary line upgrading.

Areas Affected:

Portion of Poblacion Occidental & Poblacion Oriental, Consolacion,  along portions of Cebu National Road, Central Nautical Highway, Tomas P. Go Road and H. Pepito Road.

Map:

March 26, 2026 (Thursday)

Time:

 9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Basak San Nicolas by facilitating installation of distribution transformer and extension of primary lines (line stringing).

Areas Affected:

Portion of Basak San Nicolas, Cebu City, along portions of Francisco Llamas Street.

Map:

Time:

5:00 AM to 6:00 AM (1hr)

Purpose:

To facilitate installation of loops for energization of working area.

Areas Affected:

Portion of Mandaue City & Consolacion (Basak, Cansaga, Casili, Jagobiao, Jugan, Lamac, Pitogo, Poblacion Occidental & Poblacion Oriental) along portions of Cebu National Road, Central Nautical Highway, Laray Road, M. Pepito Street, Maglasang Road, Semblante Street, & Tomas P. Go Road.

Map:

Time:

 9:00 AM to 5:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Tunghaan by facilitating relocation of primary pole as per customer request.

Areas Affected:

Portion of Tunghaan, Minglanilla, along portions of Abuno Road & Lower Tunghaan Road as well as Abuno Hills.

Map:

March 27, 2026 (Friday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Pangdan by facilitating tapping of primary lines.

Areas Affected:

Portion of Pangdan, City of Naga, along portions of Pangdan Road.

Map:

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Calamba by facilitating installation of primary lines and relocation of primary pole as per customer request.

Areas Affected:

Portion of Calamba, Cebu City, along portions of Sun Valley Drive.

Map:

Time:

7:00 AM to 5:00 PM (10hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Cotcot & Jubay by facilitating removal of primary pole and extension of primary lines (line stringing).

Areas Affected:

Portion of Cotcot & Jubay, Liloan, along portions of C. Vicinal Rd. & Cebu North Road

Map:

March 28, 2026 (Saturday)

Time:

8:00 AM to 9:00 AM (1hr)

Purpose:

To facilitate cutting of loops for isolation of working area.

Areas Affected:

Portion of Tagba-o & Taptap, Cebu City, including portions of Sitios Caba-Asan, Lobres, Paling, Proper, Tupas, & Udlom.

Map:

Time:

4:00 PM to 5:00 PM (1hr)

Purpose:

To facilitate installation of loops for energization of working area.

Areas Affected:

Portion of Tagba-o & Taptap, Cebu City, including portions of Sitios Caba-Asan, Lobres, Paling, Proper, Tupas, & Udlom.

Map:

Time:

8:00 AM to 5:00 PM (9hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Cambinocot, Lusaran, Tagba-o & Taptap by facilitating primary line upgrading.

Areas Affected:

Portion of Cambinocot, Lusaran, Tagba-o & Taptap, Cebu City, including portions of Sitios Buatis, Hagnum, Kang-atis, Pinigturan, Bombil, Caba-Asan, Lobres, Paling, Proper, Tupas, & Udlom.

Map:

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Cambinocot & Lusaran by facilitating primary line upgrading.

Areas Affected:

Portion of Cambinocot & Lusaran, Cebu City, including portions of Sitios Buatis, Hagnum, Kang-atis, Pinigturan, & Bombil.

Map:


bottom of page