September 21, 2025 (Sunday)
Time: | 8:00 AM to 5:00 PM (9hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Danglag, San Roque, Sta. Cruz, Tilhaong & Tabla by facilitating installation of primary pole and relocation of primary pole for upcoming projects. |
Areas Affected: | Portion of Danglag, San Roque, Sta. Cruz, Tilhaong & Tabla, Consolacion & Liloan, along diversion road going to Lataban road. |
Time: | 8:00 AM to 4:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Tipolo by facilitating installation of distribution transformer. |
Areas Affected: | Portion of Tipolo, Mandaue City, along Mantawi drive. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Cadulawan by facilitating installation of distribution transformer. |
Areas Affected: | Portion of Cadulawan, Talisay City, along Rio De Janeiro Street going to Vista Grande. |
Time: | 8:00 AM to 4:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Tejero by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of Tejero, Cebu City, along T.Padilla and U. Alviola Street. |
Time: | 8:00 AM to 4:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Tinago by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of Tinago, Cebu City, along Sergio Osmena Jr Blvd. |
September 22, 2025 (Monday)
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Tunghaan by facilitating installation of distribution transformer. |
Areas Affected: | Portion of Tunghaan, Minglanilla, along Estaca street. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Cansojong by facilitating installation of distribution transformer. |
Areas Affected: | Portion of Cansojong, Talisay City, along V.H. Garces and Base street. |
September 23, 2025 (Tuesday)
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Banilad by facilitating extension of primary lines (line stringing). |
Areas Affected: | Portion of Banilad, Cebu City along Paseo Don Sergio St., Paseo Elizabeth St., Paseo Sally St., and Paseo Angelina St. |
Time: | 9:00 AM to 5:00 PM (8hrs)- CANCELLED |
Purpose: | To improve the reliability of the distribution system serving Brgy. Canduman by facilitating relocation of primary pole for upcoming projects. |
Areas Affected: | Portion of Canduman, Mandaue City, along Paseo Toby Ronald Street. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Guadalupe by facilitating line reliability works of primary lines. |
Areas Affected: | Portion of Guadalupe, Cebu City, along Salvador and Lomboy Street. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Guadalupe by facilitating correction of low voltage of the distribution transformer. |
Areas Affected: | Portion of Guadalupe, Cebu City, along Don Gil Garcia Street. |
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Basak by facilitating correction of low voltage of the distribution transformer. |
Areas Affected: | Portion of Basak, Mandaue City, along Saint Jude Street. |
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Yati by facilitating replacement of primary pole. |
Areas Affected: | Portion of Yati, Liloan, along Cebu North Road. |
Time: | 9:00 AM to 12:00 PM (3hrs)-CANCELLED |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tisa by facilitating line reliability works of secondary lines. |
Areas Affected: | Portion of Tisa, Cebu City, along R.Arcenas. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Babag by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of Babag, Cebu City, along Cebu Transcentral Highway. |
September 24, 2025 (Wednesday)
Time: | 9:00 AM to 5:00 PM (8hrs)- CANCELLED |
Purpose: | To improve the reliability of the distribution system serving Brgy. Garing & Polog by facilitating relocation of primary pole for upcoming projects. |
Areas Affected: | Portion of Garing & Polog, Consolacion, going to Garing Road. |
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Poblacion Occidental by facilitating line reliability works of secondary lines. |
Areas Affected: | Portion of Poblacion Occidental, Consolacion, along Chicago and Miami Street. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Guadalupe by facilitating upgrading of distribution transformer. |
Areas Affected: | Portion of Guadalupe, Cebu City, along G. Quijada Street. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. San Isidro by facilitating reconstruction of primary lines. |
Areas Affected: | Portion of San Isidro, Talisay City along San Isidro Road and Art Ville Road. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Mabolo by facilitating secondary line maintenance. |
Areas Affected: | Portion of Mabolo, Cebu City, along J. Joaquino street. |
September 25, 2025 (Thursday)
Time: | 8:00 AM to 4:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tubod by facilitating rerouting of secondary lines. |
Areas Affected: | Portion of Tubod, Minglanilla, going to Club 30 Heights Subdivision. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Maguikay by facilitating relocation of primary pole as per customer request. |
Areas Affected: | Portion of Maguikay, Mandaue City, along portions of M.C. Briones St. |
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Camputhaw by facilitating line reliability works of primary lines. |
Areas Affected: | Portion of Camputhaw, Cebu City, along portions of Ayala Road. |
Time: | 9:00 AM to 2:00 PM (5hrs) |
Purpose: | To improve the reliability of the distribution system serving Cebu I.T. Park by facilitating removal of distribution transformer and removal of primary pole. |
Areas Affected: | Portion of Cebu I.T. Park, Cebu City, along San Miguel Rd. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Poblacion by facilitating installation of distribution transformer. |
Areas Affected: | Portion of Poblacion, Liloan, corner F. Ramas Ext and Central Nautical Hwy. |
Time: | 9:00 AM to 3:00 PM (6hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. San Roque by facilitating upgrading of the distribution transformer. |
Areas Affected: | Portion of San Roque, Talisay City, along portions of Rafael Rabaya Rd. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving South Reclamation Area by facilitating installation of distribution transformer. |
Areas Affected: | Portion of South Reclamation Area, Cebu City, along Cebu South Coastal Road. |
September 25-26, 2025 (Thursday-Friday)
Time: | 10:00 PM of September 25 to 6:00 AM of September 26 (8hrs)- CANCELLED |
Purpose: | To improve the reliability of the distribution system serving Brgy. Lawaan I, Lawaan II & Mohon by facilitating reconstruction of primary lines and installation of distribution transformer. |
Areas Affected: | Portion of Lawaan I, Lawaan II & Mohon, Talisay City, along Fidel Bas, A. Bacaltos St., and Cebu South Coastal Road, and Uldog St. |
September 26, 2025 (Friday)
Time: | 9:00 AM to 2:00 PM (5hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Labangon & Tisa by facilitating removal of distribution transformer. |
Areas Affected: | Portion of Labangon & Tisa, Cebu City, along portions of Katipunan St. and Tomlyns Compound Rd. |
Time: | 10:00 AM to 4:00 PM (6hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Tunghaan by facilitating correction of low voltage of the distribution transformer. |
Areas Affected: | Portion of Tunghaan, Minglanilla, along portions of Lower Tunghaan Road. |
September 27, 2025 (Saturday)
Time: | 8:00 AM to 5:00 PM (9hrs)- CANCELLED |
Purpose: | To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Mayana, Tagjaguimit & Uling by facilitating relocation of primary pole that is affected by road widening project. |
Areas Affected: | Portion of Mayana, Tagjaguimit & Uling, Naga City along portions of Brgy Mayana Rd., Brgy. Uling Rd. |